2014年度pmp美国项目管理考试模拟题及答案

时间:2014-05-09 16:29:00   来源:无忧考网     [字体: ]
QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be: A 4 weeks B 5 weeks C 6 weeks D 7 weeks E None of the above. B QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to: A All activities. B Only those activities with the longest time durations. C Those activities on the critical path begining with the longest time duration activities. D Those activities with the greatest degree of risk. E None of the above. C QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in: A A shortening of the critical path. B A shortening of the noncritical path. C A decrease in the total cost of the project. D An increase in the cost of the project. E A through D are possible based upon where the resources are deployed. E QUEST Bar charts are most appropriate for: A Comparing actual to planned performance to each activity. B Showing slack time. C Showing critical path dependencies. D Showing which activities can be rearranged in parallel. E All of the above. A QUEST A non-critical path activity is completed in half the time. Then, A The critical path is also reduced. B The slack in the path containing this activity will increase. C The total cost for this activity has decreased. D Manpower from this activity can be assigned to other activities. E All of the above. B QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . A Slack for each activity, critical path. B Slack for each activity, high risk activities. C Manpower shortages, high risk activities. D High risk activities, non-critical paths. E Manpower availability, contingency plans. A QUEST ADM is an activity-on-arrow method. In this method, a dummy activity: A Denotes a critical path relationship. B Denotes any dependency relationship. C Shows slack. D Identifies customer deliverables dates. E Identifies customer team meeting dates. B QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ . A Project specification tree. B Customer's deliverable list. C Customer's milestone dates. D Work breakdown structure. E Listing of customer team meeting dates. D QUEST The critical path in a network is the path that: A Has the greatest degree of risk. B Will elongate the project if the activities on this path take longer than anticipated. C Must be completed before all other paths. D All of the above. E A and B only. B QUEST The major difference between PERT and CPM networks is: A PERT requires three time estimates whereas CPM requires one time estimate. B PERT is used for construction projects whereas CPM is used for R & D. C PERT addresses only time whereas CPM also includes cost and resource availability. D PERT requires computer solutions whereas CPM is a manual technique. E PERT is measured in days whereas CPM uses weeks or months. A QUEST A calendar that identifies when a project may be performed on an activity is called a: A Project calendar. B Resource calendar. C Milestone point. D Key point. E Work unit. A QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: A Resource leveling. B Manpower leveling. C Resource limited planning. D Manpower planning. E Manpower contingency planning. C QUEST A comparison of completion status to baseline is referred to as _____. A Earned value measurement. B Percent complete. C ACWP. D BCWS E None of above. A QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: A Slack B Free float. C Restricted float. D Level float. E Lag E QUEST Overlapping activities on a project, such as design and construction, is referred to as: A Fast tracking B Risk conversion. C Parallel management. D Process improvement. E Synchronous manufacturing A QUEST A computer tape which contains historical project information is called ____ tape. A Database B Baseline. C Archive. D Lessons learned. E Life cycle summary. C QUEST Which method shown below is acceptable for reducing cost or shortening the schedule? A "Crashing" B Changing scope. C Performing activities in parallel rather than in series. D All of the above. E A and C only. D QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. A Increase, decrease. B Increase, increase C Increase, increase or decrease. D Decrease, decrease. E Decrease, increase. B QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. A Allocation. B Partitioning C Leveling D Quantification. E None of above. A QUEST Smoothing out resource requirements from period to period is called resource _____. A Allocation. B Partitioning C Leveling. D Quantification E None of above. C QUEST Guidelines for estimating time durations include: A Assuming a normal level of labor and equipment. B Assuming a normal work week. C Using consistent time units D Using past actual durations as guides. E All or part of each of the above. E QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed? A PERT B ADM C PDM D All of the above. E A and C only. C QUEST In the PDM, common constraints include: A Start-to-start B Finish-to-start C Finish-to-finish D B and C only E A, B, and C. E QUEST Activities with zero time duration are referred to as: A Critical path activites. B Noncritical path activities. C Slack time activities. D Dummies E None of above. D QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources. A Events. B Activities C Slack elements. D B and C only. E All of the above. A QUEST On a precedence diagram, the arrow between two boxes is called: A An activity. B A constraint. C An event. D The critical path. E None of above. B QUEST A project element which lies between two events is called: A An activity. B A critical path method. C A slack milestone. D A timing slot. E A calendar completion point. A QUEST The basic terminology for networks includes: A Activities, events, manpower, skill levels and slack. B Activities, documentation, events, manpower and skill levels. C Slack, activities, events, and time estimates. D Time estimates, slack, sponsorship involvement, and activities. E Time estimates, slack time, report writing, life cycle phases, and crashing times. C QUEST The utility of network-based schedules: A Reveals interdependencies. B Facilitates "what if" exercises. C Highlights critical activities. D Provides information on resource requirements, time requirements and tradeoffs. E All of the above. E QUEST The major disadvantage of a bar chart is: A Lack of time-phasing. B Cannot be related to calendar dates. C does not show activity interrelationships. D Cannot be related to manpower planning. E Cannot be related to cost estimates. C QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and: A Networks. B Time phased events. C Calendar integrated activities. D A and C only. E B and C only. A QUEST Scheduling is the process by which decisions are made concerning: A Tasks to be accomplished. B Personnel/organization that will be assigned to accomplish the task. C Time when the tasks are to be completed. D All of the above. E A and C only. E QUEST Time management is the allocation of time in a project's life cycle through the process of: A Planning B Estimating. C Scheduling. D Controlling E All of the above. E QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is: A $19K B $21K C $26K D $29K E indeterminate C QUEST Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____. A Become worse, become worse B Become worse, improved C Improved, increased D Improved, become worse E None of the above are correct B QUEST The computation for Cost Performance Index is: A BCWP/ACWP B BCWP-ACWP C BCWP-BCWS D ACWP/BCWP E ACWP-BCWS A QUEST When comparing the cost of competing projects, which of the following is typically NOT considered? A Opportunity costs. B Direct costs. C Sunk costs. D Indirect costs. E Burden rates. C QUEST The Cost Performance Index (CPI) measures: A cost of work performed vs planned costs. B work performed vs cost of work performed. C work performed vs planned work. D direct costs vs indirect costs. E floating costs vs. sunk costs. B QUEST Parametric estimates are based on variables such as: A Detailed planning and cost restraints. B Physical characteristics and historical data. C The WBS and similar projects. D Project objectives and manpower allocations. E Precise measurements and multiple inputs. B QUEST Cost and schedule data are usually integrated because: A optimized project cash flow can affect financial requirements B they provide MIS with an integrated system to produce reports C they control escalation allowances D they account for omissions in the definitive estimate E they predict future performance E QUEST Continually measuring and monitoring the actual cost versus the budget is done to _____. A analyze the reasons for variances B establish the variances C identify the problems D All of the above. E None of the above. D QUEST Using the cumulative cost curve in the special window, height B represents A actual cost to date B total budgeted costs for the project C planned cost for month 6 D cost variance E earned value B QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____. A establishing values for required functions B provide the required functions at the lowest overall cost. C identifies the required function of an item D seeks to trade performance for cost E None of the above. D QUEST The ability to achieve cost savings is inversely proportional to _____. A the earned value achieved to date B the estimated costs to complete C empowerment to the P.M. D productivity E None of the above. A